This article outlines the process for installing the NM4-I NextMeter. 

NextMeter-Indoor-Lid.svg

Installation

1. Attach meter couplings 

Secure couplings set to the water line and place new gaskets in each end.

Group_11.svg

 

2. Ensure correct spacing

The water line should be parallel and should have a spacing of 7.5" or 177.8 mm.

 

Group_13.png

Caution

Spacing should allow for meter without pushing, pulling, or kinking the line.

3. Secure the NextMeter

Place the NextMeter and tighten both ends to a max torque of 11 ft-lb using a flat jaw or monkey-style wrench.

Group_14.svg

Caution

Do NOT overtighten meer couplings as this may result in the gaskets not forming a proper seal

Pressurize the water line and check for any leaks at both connection points

Group_23.svg

 

3. Verify NextMeter communication

Open the NextMeter register lid. The Meters’s RF LED will blink green when it is able to communicate with its Gateway.

Group_8.svg

Note

The NextMeter must be programmed in the NextCentury Cloud and its Gateway must be online, in order for it to begin communicating with its Gateway.